Definitions:

Minimum Duration

The shortest time frame within which a particular task or project can be completed without delays.

Activity Duration

The time period required to complete a specific task or activity in a project.

Crash Cost

The additional costs incurred to reduce the completion time of a project or an activity, typically beyond standard operation costs.

Time-savings

The reduction in time required to perform a task, often achieved through efficiency improvements or technological advancements.