Examlex

Solved

An Activity Has an Optimistic Time Estimate of 15 Days,a

question 70

Multiple Choice

An activity has an optimistic time estimate of 15 days,a most likely estimate of 24 days,and a pessimistic estimate of 40 days.What is the variance of the activity?


Definitions:

Related Questions