Use the Network Diagram and Activity Lengths in the Nodes

question 50

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the early start time for activity D. Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.   A) 8 B) 13 C) 14 D) 21