Use the Network Diagram and Activity Lengths in the Nodes

question 87

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the late start time for activity F. Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.   A) 21 B) 24 C) 26 D) 23