Use the Network Diagram and Activity Lengths in the Nodes

question 53

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G. Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.   A) 26 B) 25 C) 24 D) 23