What Is the Late Start Time for Activity B Given

question 33

Multiple Choice

What is the late start time for Activity B given the activity times and precedence requirements shown in the table? What is the late start time for Activity B given the activity times and precedence requirements shown in the table?   A) 18 B) 9 C) 13 D) 5