What Is the Slack Time for Activity C Given the Activity

question 55

Multiple Choice

What is the slack time for Activity C given the activity times and precedence requirements shown in the table? What is the slack time for Activity C given the activity times and precedence requirements shown in the table?   A) 2 B) 1 C) 0 D) 3