It Was Well Known That the Cost of Failure Category

question 25

Multiple Choice

It was well known that the cost of failure category for cost was a 0.7,and for schedule was a 0.8.The project team settled on the cost of failure for reliability of 0.6,and for performance of 0.4.What is the overall consequence of failure?