Use the Earned Value Table to Determine the Estimated Cost

question 66

Multiple Choice

Use the earned value table to determine the estimated cost to completion (to the nearest hundred dollars) given the indicated state of the project. Use the earned value table to determine the estimated cost to completion (to the nearest hundred dollars) given the indicated state of the project.   A) $9,600 B) $7,800 C) $8,100 D) $10,500