If Resources Have Been Over-Allocated,the Loading Table Must Be Reconfigured

question 27

True/False

If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.