A Project Is Represented by the Activity Durations (Estimated at 90

question 11

Multiple Choice

A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology? A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology?   A) 9.0 B) 2.25 C) 4.5 D) 6.75


Definitions:

Repetition Statement

A programming construct that allows for the repeated execution of a block of code for a specified number of times or while a condition is true.

While Statement

A control flow statement that allows code to be executed repeatedly based on a given Boolean condition.

Expression

A combination of variables, operations, and values that produces another value.

Transfer Control

A programming action that changes the point of execution, such as jumps, loops, or calls to subroutines.

Related Questions