Your Next Project Consists of 5 Consecutive 10-Day Activities,each Estimated

question 76

Multiple Choice

Your next project consists of 5 consecutive 10-day activities,each estimated by a different worker in your organization.You have all secretly added your own safety margin of 4 days into your estimates and you watch in horror as the project manager whips out his copy of Critical Chain and slams it on the table midway through their first project meeting."I'm taking your buffers and making them my own," he bellows.You recoil from this news and do some quick mental arithmetic.Now that you know the project manager is a Goldratt disciple,you know that the new project buffer will be:


Definitions:

Cognitive Therapy

A type of psychological therapy that involves identifying and challenging negative thought patterns to alter unwanted behavior patterns or treat mood disorders.

Pathological Behavior

Actions or behaviors that are extreme or abnormal, often indicating the presence of a psychological disorder or disease.

Past Conditioning

The influence of previous experiences and learned behaviors on an individual's current actions and reactions.

Vague Feelings

Indistinct or unclear emotional states not easily defined or understood.

Related Questions