A Project Is Represented by the Activity Durations (In Days,estimated

question 20

Multiple Choice

A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology? A project is represented by the activity durations (in days,estimated at 90% likelihood of completion) and precedence requirements shown in the table.What is the length of a feeder buffer if this project is managed using critical chain methodology?   A) 4 days B) 3 days C) 2 days D) 1 days


Definitions:

Automobile Manufacturer

A company engaged in the designing, production, marketing, and selling of motor vehicles.

Sample

A subset of individuals or observations selected from a larger population, used to infer or make predictions about the population.

Poisson Distribution

A probability distribution that measures the probability of a given number of events happening in a fixed interval of time or space when these events occur with a known constant mean rate and independently of the time since the last event.

P-Value Approach

A method in statistical hypothesis testing that uses the calculated probability to determine the significance of the observed data.

Related Questions