Which of the following is not part of the systematic process called auditing?


Definitions:

Critical Path

A sequence of critical tasks in a project timeline that need timely completion to ensure the project ends on its scheduled date.

CPM Network

A project management tool that uses critical path method to model tasks and their dependencies in a project to determine the optimum project schedule.

Crashing

A project management technique used to shorten the schedule duration for the least incremental cost by adding resources to critical path tasks.

Crash Cost

The additional cost incurred to reduce the duration of a project activity or the entire project.