Assume That Funtime Corp - What Percentage Is Playground Complete?
A) 62

question 32

Multiple Choice

Assume that Funtime Corp. has agreed to construct a new playground for Durrey County for $2,300,000. Construction of the new playground will begin on March 17, 2012 and is expected to be completed in August 2013. At the signing of the contract Funtime Corp. estimates that the it will cost $1,600,000 to build the playground.
At the end of 2012 Funtime provided the following information about the project:
Costsincurred Estimated costs  Yearto date  remaining2012$1,000,000$800,000\begin{array}{llcc}& \text {Costsincurred } & \text {Estimated costs } \\\underline{ \text { Year} }& \underline{\text {to date } } & \underline{\text { remaining} }\\2012&\$1,000,000&\$800,000\\\end{array}
- What percentage is playground complete?


Definitions:

Background Image

An image set to appear behind the content in a user interface element or web page.

Other Controls

Refer to additional elements or widgets in software applications that allow users to interact with the application, beyond standard input fields.

Record Source

The source from which data is retrieved for display or processing in a database or application component.

Blank Form

An empty template designed to be filled out with information, often used in surveys, applications, or data entry tasks.

Related Questions