Magnum Construction Contracted to Construct a Factory Building for $545,000

question 8

Essay

Magnum Construction contracted to construct a factory building for $545,000. The company started during 2012 and was completed in 2013. Information relating to the contract is as follows:
20122013 Costs incurred during the year $310,000$170,000 Estimated additional cost to complete 165,000 Billings during the year 280,000285,000 Cash collections during the year 260,000305,000\begin{array}{|l|l|l|}\hline & 2012 & 2013 \\\hline \text { Costs incurred during the year } & \$ 310,000 & \$ 170,000 \\\hline \text { Estimated additional cost to complete } & 165,000 & - \\\hline \text { Billings during the year } & 280,000 & 285,000 \\\hline \text { Cash collections during the year } & 260,000 & 305,000 \\\hline\end{array}
Required:
Record the preceding transactions in Magnum's books under completed-contract and the percentage of completion methods. Determine amounts that will be reported on the balance sheet at the end of 2012.
 Conpleted-Contract Method  Year 2012 DR Construction in progress $310,000CR Cash, payables, materials, etc. $310,000DR Accounts receivable $280,000 CR Billings on contract $280,000 DR Cash $260,000 CR Accountsreceivable $260,000 Since the project is incomplete, no revenue is recogrized for the year  2012\begin{array}{llcc} \text { Conpleted-Contract Method } & \\\underline{ \text { Year 2012 } }&\\ \text {DR Construction in progress } &\$310,000\\ \text {CR Cash, payables, materials, etc. } &&\$310,000\\ \text {DR Accounts receivable } &\$280,000\\ \text { CR Billings on contract } &\$280,000&\\ \text { DR Cash } &\$260,000\\ \text { CR Accountsreceivable } &&\$260,000\\ \text { Since the project is incomplete, no revenue is recogrized for the } &\\ \text {year } &\\ \text { 2012} &\\\end{array}
 Magnum Construction contracted to construct a factory building for $545,000. The company started during 2012 and was completed in 2013. Information relating to the contract is as follows:   \begin{array}{|l|l|l|} \hline & 2012 & 2013 \\ \hline \text { Costs incurred during the year } & \$ 310,000 & \$ 170,000 \\ \hline \text { Estimated additional cost to complete } & 165,000 & - \\ \hline \text { Billings during the year } & 280,000 & 285,000 \\ \hline \text { Cash collections during the year } & 260,000 & 305,000 \\ \hline \end{array}   Required: Record the preceding transactions in Magnum's books under completed-contract and the percentage of completion methods. Determine amounts that will be reported on the balance sheet at the end of 2012.   \begin{array}{llcc}   \text { Conpleted-Contract Method } &  \\ \underline{ \text { Year 2012 } }&\\  \text {DR Construction in progress  } &\$310,000\\  \text {CR Cash, payables, materials, etc.  } &&\$310,000\\  \text {DR Accounts receivable  } &\$280,000\\  \text { CR Billings on contract } &\$280,000&\\  \text { DR Cash } &\$260,000\\  \text { CR Accountsreceivable } &&\$260,000\\  \text { Since the project is incomplete, no revenue is recogrized for the } &\\  \text {year  } &\\  \text {  2012} &\\ \end{array}      \begin{array}{llcc}   \text {  Percentige-of-Conpletion Method} &  \\ \underline{  \text {  Year 2012}}\\  \text { DR Construction in progress } &\$310,000\\  \text {CR Cash, payables, materials, etc.  } &&\$310,000\\  \text { DR Accounts receivable } &\$280,000\\  \text { CR Billings on contract } &&\$280,000\\  \text {DR Cash  } &\$260,000\\  \text {  CR Accountsreceivable} &&\$260,000\\ \end{array}    \begin{array}{llcc}   \text {DR Construction in progress'  } &\$45,684  \\  \text { CR Income onlong-term   } &\\  \text {  construction contracts} &&\$45,684\\ \underline{\text {Alteminte entry:}}\\  \text {  DR Construction in progress} &\$45,68\\  \text { DR Construction expense } &4\\  \text { CR Construction revenue* } &310,000&\$355,684\\  \text { Contract price  } &&\$545,000\\  \text { - Actual coststo date } &(\$310,000)\\  \text { - Estimated costs to complete } &\underline{(165,000)}\\  \text {Total estimated costs of project  } &&\underline{(475,00)}\\  \text { Estimated total grossmargin } &&\$70,000\\ \end{array}      Percentige-of-Conpletion Method Year 2012 DR Construction in progress $310,000CR Cash, payables, materials, etc. $310,000 DR Accounts receivable $280,000 CR Billings on contract $280,000DR Cash $260,000 CR Accountsreceivable$260,000\begin{array}{llcc} \text { Percentige-of-Conpletion Method} & \\\underline{ \text { Year 2012}}\\ \text { DR Construction in progress } &\$310,000\\ \text {CR Cash, payables, materials, etc. } &&\$310,000\\ \text { DR Accounts receivable } &\$280,000\\ \text { CR Billings on contract } &&\$280,000\\ \text {DR Cash } &\$260,000\\ \text { CR Accountsreceivable} &&\$260,000\\\end{array}
DR Construction in progress’ $45,684 CR Income onlong-term  construction contracts$45,684Alteminte entry: DR Construction in progress$45,68 DR Construction expense 4 CR Construction revenue* 310,000$355,684"Contract price $545,000 - Actual coststo date ($310,000) - Estimated costs to complete (165,000)Total estimated costs of project (475,00) Estimated total grossmargin $70,000\begin{array}{llcc} \text {DR Construction in progress' } &\$45,684 \\ \text { CR Income onlong-term } &\\ \text { construction contracts} &&\$45,684\\\underline{\text {Alteminte entry:}}\\ \text { DR Construction in progress} &\$45,68\\ \text { DR Construction expense } &4\\ \text { CR Construction revenue* } &310,000&\$355,684\\ \text {"Contract price } &&\$545,000\\ \text { - Actual coststo date } &(\$310,000)\\ \text { - Estimated costs to complete } &\underline{(165,000)}\\ \text {Total estimated costs of project } &&\underline{(475,00)}\\ \text { Estimated total grossmargin } &&\$70,000\\\end{array}
 Magnum Construction contracted to construct a factory building for $545,000. The company started during 2012 and was completed in 2013. Information relating to the contract is as follows:   \begin{array}{|l|l|l|} \hline & 2012 & 2013 \\ \hline \text { Costs incurred during the year } & \$ 310,000 & \$ 170,000 \\ \hline \text { Estimated additional cost to complete } & 165,000 & - \\ \hline \text { Billings during the year } & 280,000 & 285,000 \\ \hline \text { Cash collections during the year } & 260,000 & 305,000 \\ \hline \end{array}   Required: Record the preceding transactions in Magnum's books under completed-contract and the percentage of completion methods. Determine amounts that will be reported on the balance sheet at the end of 2012.   \begin{array}{llcc}   \text { Conpleted-Contract Method } &  \\ \underline{ \text { Year 2012 } }&\\  \text {DR Construction in progress  } &\$310,000\\  \text {CR Cash, payables, materials, etc.  } &&\$310,000\\  \text {DR Accounts receivable  } &\$280,000\\  \text { CR Billings on contract } &\$280,000&\\  \text { DR Cash } &\$260,000\\  \text { CR Accountsreceivable } &&\$260,000\\  \text { Since the project is incomplete, no revenue is recogrized for the } &\\  \text {year  } &\\  \text {  2012} &\\ \end{array}      \begin{array}{llcc}   \text {  Percentige-of-Conpletion Method} &  \\ \underline{  \text {  Year 2012}}\\  \text { DR Construction in progress } &\$310,000\\  \text {CR Cash, payables, materials, etc.  } &&\$310,000\\  \text { DR Accounts receivable } &\$280,000\\  \text { CR Billings on contract } &&\$280,000\\  \text {DR Cash  } &\$260,000\\  \text {  CR Accountsreceivable} &&\$260,000\\ \end{array}    \begin{array}{llcc}   \text {DR Construction in progress'  } &\$45,684  \\  \text { CR Income onlong-term   } &\\  \text {  construction contracts} &&\$45,684\\ \underline{\text {Alteminte entry:}}\\  \text {  DR Construction in progress} &\$45,68\\  \text { DR Construction expense } &4\\  \text { CR Construction revenue* } &310,000&\$355,684\\  \text { Contract price  } &&\$545,000\\  \text { - Actual coststo date } &(\$310,000)\\  \text { - Estimated costs to complete } &\underline{(165,000)}\\  \text {Total estimated costs of project  } &&\underline{(475,00)}\\  \text { Estimated total grossmargin } &&\$70,000\\ \end{array}


Definitions:

Coping Strategy

Methods or techniques used by individuals to handle stress, manage problems, or adjust to psychological distress.

Reappraising

The cognitive process of changing one's emotional response to a situation by altering one's interpretation of that situation.

Inauthentic Expression

A display of emotions or feelings that does not genuinely reflect what one is actually experiencing.

Authentic Emotions

Genuine feelings that are experienced and expressed congruently with one's true emotional state.

Related Questions