Activity Durations
The estimated time periods that tasks or activities within a project are expected to take to complete.
Project Duration
The total time taken to complete a project from its start to finish, often used in planning and scheduling.
Expected Duration
The estimated time needed to complete a project or task, often considering various uncertainties or risk factors.
Critical Path
A continuity of necessary tasks in a project's agenda that have to be accomplished on time for the project to meet its proposed finalization date.
Q3: Joyce wants to stop recording the steps
Q12: To edit placeholder text in a chart
Q16: Sophia is putting together a training manual
Q21: Issac wants to add a border to
Q22: How are delivery drivers able to meet
Q24: Arlo creates a rectangular shape and inserts
Q36: Where on a computer is the operating
Q37: You can create conditional cell formats using
Q53: A short advertisement film needs to be
Q59: Alicia often uses short,engaging videos to engage