Assume That Jobs A-D Arrive in the READY Queue in Quick

question 20

Multiple Choice

Assume that jobs A-D arrive in the READY queue in quick succession and have the CPU cycle requirements listed below.Using the SRT algorithm,the average turnaround time is ____. Arrival time: 0 1 2 3
Job: A B C D
CPU cycle: 6 3 1 4