The First Unit of a Product Took 832 Hours to Build

question 46

Multiple Choice

The first unit of a product took 832 hours to build, and the learning curve is 75%. How long will it take to make the 10th unit? (Use at least three decimals in the exponent if you use the logarithmic approach.)