You Are About to Undertake Manufacture of a Labour-Intensive Electronics

question 104

Essay

You are about to undertake manufacture of a labour-intensive electronics component. The first unit took 300 hours. You are not sure whether the learning rate is 70% or 80%. The initial phase of the contract calls for 6 of these components.
a. How much time will it take to complete all six at 70% learning?
b. How much time will it take to complete all six at 80% learning?