You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units per eight-hour day. Task times and precedence relationships are shown in the table below.
a. Draw the precedence diagram.
b. Determine the desired cycle time.
c. Determine the theoretical minimum number of stations needed.
d. Balance this line using most following tasks.
e. What is the efficiency of the line obtained in part d?
Variable Cost
Costs that fluctuate in direct proportion to production or sales figures, including items like direct labor and raw materials.
Mixed Costs
Expenses comprising both fixed and variable components, changing in total with the level of activity but not proportionately.
Merchandising Firm
A business that purchases finished goods for resale in order to make a profit, differentiating itself from manufacturing firms and service firms.
Gross Margin
The difference between sales revenue and the cost of goods sold, expressed as a percentage of sales revenue.
Q34: Continuous improvement is based on the philosophy
Q60: A hospital benchmarked against Ferrari Racing in
Q61: An assembly line has been designed
Q61: Daily sales of bread by Salvador
Q71: The _ develops an initial feasible solution
Q74: An operations manager's staff has compiled
Q85: What are the advantages and disadvantages of
Q131: High fixed costs and low variable costs
Q138: Location decisions are based on many things,
Q164: Which of the following is not one