An Assembly Line with 11 Tasks Is to Be Balanced

question 15

Essay

An assembly line with 11 tasks is to be balanced.The longest task is 2.4 minutes,the shortest task is 0.4 minutes,and the sum of the task times is 18 minutes.The line will operate for 600 minutes per day.
(a)Determine the minimum and maximum cycle times.
(b)What range of output is theoretically possible for the line?
(c)What is the minimum number of stations needed if the maximum output rate is to be sought?
(d)What cycle time will provide an output rate of 200 units per day?


Definitions:

First-stage Allocation

The process in cost accounting of assigning overhead costs to various cost pools before they are allocated to products or services.

Activity-based Costing

This costing method assigns overhead and indirect costs to specific activities, providing more accurate insights into the actual costs of production or service delivery.

Resource Consumption

The amount of resources used by an activity, process, or production.

Activity-based Costing

A costing method that assigns overhead and indirect costs to related products and services based on the activities that drive those costs.

Related Questions