An assembly line with 11 tasks is to be balanced. The longest task is 2.5 minutes, the shortest task is 0.5 minutes, and the sum of the task times is 20 minutes. The line will operate for 700 minutes per day.
a. Determine the minimum and maximum cycle times.
b. What range of output is theoretically possible for the line?
c. What is the minimum number of stations needed if the maximum output rate is to be sought?
d. What cycle time will provide an output rate of 200 units per day?
Addiction
A complex condition characterized by persistent use of substances or engagement in behaviors despite harmful consequences.
Follow-Up
The process of monitoring, contacting, or checking in after an initial event, meeting, or treatment to ensure progress or address any subsequent issues.
Alcoholism Recovery
The process of overcoming the dependence on alcohol and rebuilding one's life.
Q30: In the Office Relationship Chart, which rating
Q40: Explain how a Pareto chart can identify
Q41: _ costs are readily identifiable and can
Q55: Perform a Pareto analysis on the
Q91: A branch of a decision tree that
Q102: What is the difference between a feasible
Q105: Describe how ISO 9000 has evolved in
Q108: Globalization of the location decision is the
Q149: A firm is considering two location alternatives.
Q157: A work cell is required to make