Given the Critical Path Below, Calculate the Following
A

question 125

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $7000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0006 days $12,000 B 5 days $2,0002 days $9,500 C 10 days $9,0008 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 6 \text { days } & \$ 12,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 2 \text { days } & \$ 9,500 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 8 \text { days } & \$ 12,000 \\\hline\end{array}

Solve problems involving graduated commission plans.
Calculate total costs with additional fees and commissions.
Assess financial outcomes for third-party service commissions.
Apply percentage-based calculations to real-world problems.

Definitions:

Childhood Obesity

A serious medical condition affecting children and adolescents, characterized by exceeding the healthy weight for one's age and height.

Popularity

The status of being favored, esteemed, or backed by a large number of individuals.

Sexual Attractiveness

The degree to which an individual’s physical features, behaviors, and traits are perceived as appealing or desirable in a potential sexual partner.

Social Skills

The abilities used by individuals to interact and communicate with others effectively through verbal and non-verbal means, encompassing behaviors such as turn-taking, listening, and understanding social cues.

Related Questions