Examlex

Solved

Given the Critical Path Below, Calculate the Following
A

question 85

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $6000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0005 days $11,000 B 5 days $2,0002 days $9,500 C 10 days $9,0008 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 5 \text { days } & \$ 11,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 2 \text { days } & \$ 9,500 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 8 \text { days } & \$ 12,000 \\\hline\end{array}


Definitions:

Exclusive Jurisdiction

Jurisdiction that exists when a case can be heard only in a particular court, such as a federal court.

Acts of Congress

Legislation enacted by the United States Congress, which becomes law either upon presidential approval or through overriding a presidential veto.

Trial Court

A court in which cases begin and in which questions of fact are examined.

Questions of Fact

Issues in a legal case that are related to the determination of what actually happened, as opposed to questions of law which involve the interpretation of the law.

Related Questions