The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6. The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.   a. What task must be on the critical path, regardless of activity durations? b. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? e. What is slack time at activity H? f. What is the Late Finish of activity H? g. If activity C were delayed by two time units, what would happen to the project duration? a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?


Definitions:

Less Bureaucratic

Referring to organizations or systems operating with fewer rules, formalities, and administrative procedures, aiming for greater flexibility and efficiency.

Servant Leader

A leadership philosophy which emphasizes the leader's primary role as serving the needs of their team members or employees.

Self-Determination

The process by which individuals control their own life, make their own decisions, and pursue their own goals, often in the context of nations or psychological development.

Meaning

The significance, purpose, or understanding of something, often related to how it is perceived or interpreted by individuals.

Related Questions