Examlex

Solved

A Network Consists of the Following List A Draw the Network Diagram

question 90

Essay

A network consists of the following list. Times are given in weeks.
 Activity  Preceding  Duration  A 9 B A2 C A12 D A5 E B6 F B8 G C,F3 H D2 I H8 J  G, I 6 K  E, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Duration } \\\hline \text { A } & - - & 9 \\\hline \text { B } & \mathrm { A } & 2 \\\hline \text { C } & \mathrm { A } & 12 \\\hline \text { D } & \mathrm { A } & 5 \\\hline \text { E } & \mathrm { B } & 6 \\\hline \text { F } & \mathrm { B } & 8 \\\hline \text { G } & \mathrm { C } , \mathrm { F } & 3 \\\hline \text { H } & \mathrm { D } & 2 \\\hline \text { I } & \mathrm { H } & 8 \\\hline \text { J } & \text { G, I } & 6 \\\hline \text { K } & \text { E, J } & 2 \\\hline\end{array} a. Draw the network diagram.
b. Which activities form the critical path?
c. How much slack exists at activities A and F?
d. What is the duration of the critical path?


Definitions:

Brainstorming Sessions

Interactive meetings where participants generate creative ideas and solutions in a collaborative environment.

Project Manager

A professional responsible for planning, executing, and closing projects, overseeing the project team, timeline, resources, and deliverables.

High-performance Work Systems

A set of management practices designed to create an environment where employees can effectively utilize their skills and abilities to achieve high levels of performance.

Social System

An organized and interdependent set of roles, norms, and processes that people use to interact and cooperate within a society or a specific group.

Related Questions