Consider the network presented in the following table. Calculate
a. All possible paths
b. The critical path
c. The slack available at any non-critical points
d. The minimum project duration
 Task  Duration  (Days)  Immediate  Predecessors  A 5 None  B 3 A  C 4 A D 2 C  E 1 B, D \begin{array} { | c | c | c | } \hline \text { Task } & \begin{array} { c } \text { Duration } \\\text { (Days) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 5 & \text { None } \\\hline \text { B } & 3 & \text { A } \\\hline \text { C } & 4 & \mathrm {~A} \\\hline \text { D } & 2 & \text { C } \\\hline \text { E } & 1 & \text { B, D } \\\hline\end{array}


Definitions:

Consumer Price Index

A measure that examines the weighted average of prices of a basket of consumer goods and services, typically used as an indicator of inflation.

Economy Expanding

A phase where a nation's economic activity is growing, marked by increased production, employment, and consumption.

Recessions

Economic downturns marked by decreasing industrial production, employment, and sales, often lasting from a few months to more than a year.

Frictional Unemployment

The short-term unemployment that arises from the process of workers moving between jobs or into the labor market.

Related Questions