A Simple CPM Network Has Three Activities,A,B,and C

question 31

Multiple Choice

A simple CPM network has three activities,A,B,and C.A is an immediate predecessor of B and of C.B is an immediate predecessor of C.The activity durations are A=4,B=3,C=8.