Two Critical Path Activities Are Candidates for Crashing on a CPM

question 108

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.  Activity  Normal Time  Normal Cost  Crash Time  Crash Cost  B 4 days $6,0003 days $8,000 C 6 days $4,0004 days $6,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \text { Crash Time } & \text { Crash Cost } \\\hline \text { B } & 4 \text { days } & \$ 6,000 & 3 \text { days } & \$ 8,000 \\\hline \text { C } & 6 \text { days } & \$ 4,000 & 4 \text { days } & \$ 6,000 \\\hline\end{array}


Definitions:

Sherman Act

A landmark federal statute in the field of United States antitrust law passed in 1890 that prohibits certain business activities that reduce competition in the marketplace.

Clayton Act

A U.S. antitrust law aimed at increasing competition by preventing unfair trade practices and monopolies.

Federal Trade Commission Act

A U.S. federal law established in 1914 to prevent unfair or deceptive business practices, including anti-trust laws, to promote fair competition.

Social Regulation

Rules and standards imposed by governments to protect public welfare, including health, safety, and the environment.

Related Questions