A Project Being Analyzed by PERT Has 50 Activities, 12

question 115

Multiple Choice

A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the critical path is 176 days with a project variance of 144, the probability that the project will take 194 days or less to complete is