Given the Critical Path Below, Calculate the Following
A

question 85

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $6000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0005 days $11,000 B 5 days $2,0002 days $9,500 C 10 days $9,0008 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 5 \text { days } & \$ 11,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 2 \text { days } & \$ 9,500 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 8 \text { days } & \$ 12,000 \\\hline\end{array}


Definitions:

White Rat

Often used in psychological experiments, a white rat is a specially bred rat for research that is distinguished by its albino coloring.

Higher-Order Conditioning

A form of learning in which a stimulus is paired with a previously conditioned stimulus, creating the same response without direct conditioning to the original unconditioned stimulus.

Metronome Sound

The sound produced by a metronome, used to mark time at a selected rate by producing regular ticks.

Pavlov

Pavlov, Ivan Petrovich, was a Russian physiologist known for his work in classical conditioning, demonstrating learned responses through his experiments with dogs and bell stimuli.

Related Questions