A network consists of the following list. Times are given in weeks.
 Activity  Preceding  Duration  A 9 B A2 C A12 D A5 E B6 F B8 G C,F3 H D2 I H8 J  G, I 6 K  E, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Duration } \\\hline \text { A } & - - & 9 \\\hline \text { B } & \mathrm { A } & 2 \\\hline \text { C } & \mathrm { A } & 12 \\\hline \text { D } & \mathrm { A } & 5 \\\hline \text { E } & \mathrm { B } & 6 \\\hline \text { F } & \mathrm { B } & 8 \\\hline \text { G } & \mathrm { C } , \mathrm { F } & 3 \\\hline \text { H } & \mathrm { D } & 2 \\\hline \text { I } & \mathrm { H } & 8 \\\hline \text { J } & \text { G, I } & 6 \\\hline \text { K } & \text { E, J } & 2 \\\hline\end{array} a. Draw the network diagram.
b. Which activities form the critical path?
c. How much slack exists at activities A and F?
d. What is the duration of the critical path?


Definitions:

Service Period

The specified timeframe during which a service is offered or obligated to be performed.

Original Contract

The initial agreement or set of terms established between parties before a project or service is executed.

Closure

The act of bringing something to an end or conclusion.

Limit Time

refers to setting a fixed duration for a specific activity or process to be completed.

Related Questions