A network consists of the following list. Times are given in weeks.
 Activity  Preceding  Duration  A 9 B A2 C A12 D A5 E B6 F B8 G C,F3 H D2 I H8 J  G, I 6 K  E, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Preceding } & \text { Duration } \\\hline \text { A } & - - & 9 \\\hline \text { B } & \mathrm { A } & 2 \\\hline \text { C } & \mathrm { A } & 12 \\\hline \text { D } & \mathrm { A } & 5 \\\hline \text { E } & \mathrm { B } & 6 \\\hline \text { F } & \mathrm { B } & 8 \\\hline \text { G } & \mathrm { C } , \mathrm { F } & 3 \\\hline \text { H } & \mathrm { D } & 2 \\\hline \text { I } & \mathrm { H } & 8 \\\hline \text { J } & \text { G, I } & 6 \\\hline \text { K } & \text { E, J } & 2 \\\hline\end{array} a. Draw the network diagram.
b. Which activities form the critical path?
c. How much slack exists at activities A and F?
d. What is the duration of the critical path?


Definitions:

Communist Central Planning

A system where the government makes all decisions about the production and allocation of goods and services in an economy.

Personal Gain

The benefit or advantage one receives or aims to receive from an action or investment, often measured in terms of financial or personal satisfaction.

Market System

A system of economics where the choices about investment, production, and distribution rely on the principles of supply and demand, and the pricing of goods and services is established freely in the market.

Business Risk

The potential for losses or less than expected returns stemming from the operational aspects of a business.

Related Questions