Given the Project Within the Table Below Calculate
A

question 37

Essay

Given the project within the table below calculate
a. The critical path
b. The minimum project duration
c. The amount of slack for each activity
 Activity  Duration  (hours)  Immediate  Predecessors A4 None B3 None C10 None D7 B,CE1DF1EG5 A, F\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (hours) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \mathrm { A } & 4 & \text { None } \\\hline \mathrm { B } & 3 & \text { None } \\\hline \mathrm { C } & 10 & \text { None } \\\hline \mathrm { D } & 7 & \mathrm {~B} , \mathrm { C } \\\hline \mathrm { E } & 1 & \mathrm { D } \\\hline \mathrm { F } & 1 & \mathrm { E } \\\hline \mathrm { G } & 5 & \mathrm {~A} , \mathrm {~F} \\\hline\end{array}


Definitions:

Reasons For Decisions

The rationale or underlying factors that lead to a particular choice or judgment being made.

Apologize

Expressing regret or asking for forgiveness for an action or statement.

Negative Message

Communication that conveys a refusal, denial, or unwelcome news to the receiver.

Sincere Apology

An expression of regret that is genuine and heartfelt, indicating true remorse for actions or words that caused harm.

Related Questions