Given the Critical Path Below, Calculate the Following
A

question 121

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $3000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0007 days $12,000 B 5 days $2,0003 days $10,000 C 10 days $9,0009 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 7 \text { days } & \$ 12,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 3 \text { days } & \$ 10,000 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 9 \text { days } & \$ 12,000 \\\hline\end{array}


Definitions:

Being Too Cold

Often refers to a demeanor or attitude perceived as distant, unemotional, or lacking in warmth and friendliness.

Southern States

Geographical regions located in the southern part of the United States, characterized by distinct cultural, historical, and social traits.

Retaliate

Taking revenge or responding to an injury or wrong experienced, often by committing a similar act of aggression or harm.

Insult

A disrespectful or scornful remark directed at someone, often with the intent to offend.

Related Questions