The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time (makespan) to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
a. Chart the progress of these five jobs through the two centres on the basis of the arbitrary order
A→B→C→D→E.
b. After how many hours will all jobs be completed?
c. Use Johnson's rule to sequence these five jobs for minimum total duration. Show your work in
determining the job sequence.
d. The optimal sequence is ________.
e. Chart the progress of the five jobs in this optimal sequence.
f. After how many hours will all jobs be completed?
Crash Duration
The shortest possible time for which an activity or project phase can be scheduled after allocating the maximum amount of resources.
Total Cost
The complete cost of producing or acquiring goods or services, including variable costs, fixed costs, and any other relevant expenses.
Network Diagram
A visual representation of a project's activities and their interdependencies, often used to plan and monitor project timelines.
Expected Duration
The anticipated amount of time which will elapse before a particular project or activity is completed.
Q3: Time fences divide that segment of the
Q14: The use of part-time workers as an
Q14: Which of the following statements best compares
Q22: Use of the shortest processing time sequencing
Q39: A bakery uses 6 containers that each
Q40: Which of the international operations strategies involves
Q53: Which of these is among the demand
Q55: Level scheduling means producing at a constant
Q84: Which of the following statements regarding aggregate
Q131: One criterion for developing effective schedules is