Bob Dresser operates a major appliance warranty service centre. His operation has two check stations that are required at the end of every repair task performed by his appliance repair staff. These are the Functionality Review (FR) and the Overall Scan (OS). The FR must be performed successfully before the OS is begun. On Friday morning, six repair jobs are completed, awaiting these two inspection activities. Processing times are given in minutes.
a. What is the optimal sequence of jobs for the objective of minimizing the total flow time?
b. Show your work, and document the sequence.
c. Chart the solution to this problem.
d. What jobs are being processed at time period 90?
e. What is the total flow time of this problem?
Short-term
Relating to or occurring on a brief or immediate timescale, typically within one year, used especially in finance and investment contexts.
Q1: Standardization is an appropriate strategy in which
Q48: Identify the types of planning files used
Q61: The president of a consulting firm
Q72: Labor cost for set-up is $500/hour.
Q109: What is the typical planning horizon for
Q114: The strategies of aggregate planning are broadly
Q125: Which of the following is not included
Q139: Define maintenance.
Q141: The assumptions of the production order quantity
Q168: What are the assumptions of the EOQ