A manufacturer has the following jobs waiting on a single work centre. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time in 15-minute time blocks and due date for each job are in the table below.
 Time  Due Date  Job 1 517 Job 2 420 Job 3 316 Job 4 79 Job 5 36 Job 6 57\begin{array} { | c | c | c | } \hline & \text { Time } & \text { Due Date } \\\hline \text { Job 1 } & 5 & 17 \\\hline \text { Job 2 } & 4 & 20 \\\hline \text { Job 3 } & 3 & 16 \\\hline \text { Job 4 } & 7 & 9 \\\hline \text { Job 5 } & 3 & 6 \\\hline \text { Job 6 } & 5 & 7 \\\hline\end{array} a. Complete the following table. Show your supporting calculations below.
b. Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness?
c. Is there ANY sequence that can avoid all lateness? Explain or provide an example.
 Dispatching  Average  Average  Average  Rule  Job Sequence  Flow Time  Number of Jobs  Lateness  EDD  SPT  LPT \begin{array}{|l|l|l|l|l|}\hline\text { Dispatching } & & \text { Average } & \text { Average } & \text { Average } \\\text { Rule } & \text { Job Sequence } & \text { Flow Time } & \text { Number of Jobs } & \text { Lateness } \\\hline \text { EDD } & & & & \\\hline \text { SPT } & & & & \\\hline \text { LPT } & & & & \\\hline\end{array}