question 103

Multiple Choice

Each R requires 4 of component S; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for the procurement of T is 6 weeks. The cumulative lead time for R is __________ weeks.


Definitions:

Double-Declining-Balance

A method of accelerated depreciation in which an asset's book value is reduced by double the rate of its straight-line depreciation.

Crane

A tall machine used for moving heavy objects by suspending them from a projecting arm or beam.

Sum-Of-The-Years-Digits

A depreciation method that accelerates the recognition of expenses by applying a decreasing fraction to the depreciable value each year, based on the sum of the years’ digits.

Office Furniture

Items and fixtures used in an office setting for working and storage purposes, including desks, chairs, and file cabinets.