If the Following Jobs Are Sequenced According to the First-Come-First-Served

question 72

Multiple Choice

If the following jobs are sequenced according to the first-come-first-served (FCFS) rule,then the mean completion time in days for all jobs is (assume zero for today's date) If the following jobs are sequenced according to the first-come-first-served (FCFS) rule,then the mean completion time in days for all jobs is (assume zero for today's date)    A) 33 days. B) 22 days. C) 6.6 days. D) 4.4 days.