The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the variance for activity E is A) 1.291. B) 1.667. C) 2.582. D) 2.778.
Table 9.2
-Using Table 9.2,the variance for activity E is


Definitions:

Held-to-Maturity Debt Securities

Debt securities that a company has the intent and ability to hold until they mature.

Impairment Loss

The amount by which the carrying value of an asset exceeds its recoverable value, necessitating a write-down of the asset’s value on the balance sheet.

IFRS

International Financial Reporting Standards, which are a set of accounting rules used globally to prepare and present financial statements.

Foreign Currency Transaction

A business operation involving the exchange of currencies from two different countries.

Related Questions