Given the Tasks,estimated Durations,and Crash Costs Shown Below,what Would Be

question 26

Multiple Choice

Given the tasks,estimated durations,and crash costs shown below,what would be the minimum cost to reduce the project by one day? Given the tasks,estimated durations,and crash costs shown below,what would be the minimum cost to reduce the project by one day?   A) $200 B) $500 C) $700 D) $800 E) $1,000