A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:   What is the likelihood the project will be completed in 10 days? A) Between 88 and 88 percent B) Between 89 and 92 percent C) Between 93 and 97 percent D) Between 98 and 100 percent What is the likelihood the project will be completed in 10 days?


Definitions:

Communicating

The act of conveying information or expressing thoughts and feelings through speech, writing, signals, or behavior.

Bystanders

Individuals who are present at an event or incident but do not take an active role in its outcome.

Audiences

Groups of listeners, viewers, or spectators that observe, follow, or listen to a particular event, performance, or communication.

Accountability

The obligation of an individual or organization to account for its activities, accept responsibility for them, and to disclose the results in a transparent manner.

Related Questions