The Figure Below Shows the Tasks Required to Complete a Project

question 21

Multiple Choice

The figure below shows the tasks required to complete a project and the expected duration for each task. The figure below shows the tasks required to complete a project and the expected duration for each task.   How long should we expect it to take to complete this project? A) 20 weeks B) 38 weeks C) 21 weeks D) None of these are correct How long should we expect it to take to complete this project?