On January 1, 2011 Rose Enterprises obtained a contract to construct a building. It was estimated at the beginning of the contract that it would take three years to complete the project at an expected cost of $200,000. The contract price was $250,000. The following information describes the status of the job at the close of production each year:
On January 1, 2011 Rose Enterprises obtained a contract to construct a building. It was estimated at the beginning of the contract that it would take three years to complete the project at an expected cost of $200,000. The contract price was $250,000. The following information describes the status of the job at the close of production each year:     Compute the items listed below for each year assuming the use of the percentage-of-completion cost-to-cost method. (Round all percentages to two decimals).
Compute the items listed below for each year assuming the use of the percentage-of-completion cost-to-cost method. (Round all percentages to two decimals).
On January 1, 2011 Rose Enterprises obtained a contract to construct a building. It was estimated at the beginning of the contract that it would take three years to complete the project at an expected cost of $200,000. The contract price was $250,000. The following information describes the status of the job at the close of production each year:     Compute the items listed below for each year assuming the use of the percentage-of-completion cost-to-cost method. (Round all percentages to two decimals).
On January 1, 2011 Rose Enterprises obtained a contract to construct a building. It was estimated at the beginning of the contract that it would take three years to complete the project at an expected cost of $200,000. The contract price was $250,000. The following information describes the status of the job at the close of production each year:     Compute the items listed below for each year assuming the use of the percentage-of-completion cost-to-cost method. (Round all percentages to two decimals).