question 36
Multiple Choice
Conversion Factors for the Cumulative Average Number of Direct Labor Hours per Unit
80% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.900000.834030.785530.747550.716570.690560.668240.648760.631540.616130.602240.589600.578020.567370.557510.548340.53979n1920212223242526272829303132333435360.537180.524250.517150.510450.504100.498080.492340.486880.481670.476680.471910.467330.462930.458710.464640.450720.446940.44329n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.439760.436340.433040.429840.373820.302690.244050.196220.186610.177710.170340.164080.158670.149720.142540.136600.131550.1272090% Learning Rate ( n= cumulative production) n1234567891011121314151617181.000000.950000.915400.889050.867840.850130.834960.821720.809980.799450.789910.781200.773200.765800.758910.752490.746460.74080n1920212223242526272829303132333435360.735450.730390.725590.721020.716660.712510.708530.704720.701060.697540.694160.690900.687750.674710.681770.678930.676170.67350n37383940641282565126007008009001,0001,2001,4001,6001,8002,0000.670910.668390.665950.663570.620430.560690.505860.455940.445190.434960.426290.418780.412170.400970.391730.383900.377110.37114
-Given that the fifth unit took 10 hours to build and the learning rate is 90 percent,how much time will it take to build units 11 through 15? Refer to the copy of Table G.1 above.
Definitions:
Forecasts
Predictions about future events, conditions, or trends based on current data or analysis, used to assist in planning and decision-making.
Shortsighted Emphasis
A focus on immediate outcomes without considering long-term implications.
Organizational Strategy
A plan devised by an organization to achieve long-term goals and sustain competitive advantage.
Stopgap Hiring
A temporary recruitment solution to fill urgent vacancies while looking for permanent staff.