High Tech, Inc The Sawing Machines Operate on Two 8-Hour Shifts, 5 Days

question 120

Multiple Choice

Table 4.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.

 Time Standard  Demand Forecasts ( 000 units/yr)   Product  Processing  Setup  Batch Size  Pessimistic  Expected  Optimistic  A .202.040200240300 B .153.050160180200\begin{array}{c}\quad\quad\quad\quad\quad\text { Time Standard } \quad\quad \quad\quad\quad\quad\quad \text { Demand Forecasts ( 000 units/yr) }\\\begin{array}{|l|l|l|l|l|l|l|}\hline \text { Product } & \text { Processing } & \text { Setup } & \text { Batch Size } & \text { Pessimistic } & \text { Expected } & \text { Optimistic } \\\hline \text { A } & .20 & 2.0 & 40 & 200 & 240 & 300 \\\text { B } & .15 & 3.0 & 50 & 160 & 180 & 200 \\\hline\end{array}\end{array}
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 4.2,what is the minimum number of machines needed (assuming no reliance on short-term options) ?


Definitions:

Money Income

The total amount of monetary earnings received by an individual or household, including wages, salaries, and other forms of financial income.

Budget Constraint

The limit set by available resources, defining the combination of goods or services that a consumer can afford.

Money Income

The total amount of monetary earnings received by an individual or group, including wages, salaries, bonuses, and other income.

Choice Set

A set of options available for a decision-maker to choose from in a given scenario.

Related Questions