Table 7.3 a Company Uses a Kanban System. the Daily Demand for Demand

question 65

Multiple Choice

Table 7.3
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is 0.2 day. The processing time for a container of part A is 0.8 day, and a container holds 300 units.
-Use the information in Table 7.3.How many kanban containers would be required if a 5 % efficiency factor is used?


Definitions:

Auditory Stimulation

The exposure to sound or noise, which can influence brain activity and behavior, being critical in processes like learning and communication.

Visual Stimuli

External cues or objects within the environment that are seen and can influence a person's behavior or emotional state.

Scientific Term

A word or phrase typically used in scientific literature to describe specific concepts, processes, or entities in a concise and precise manner.

Rehearsal

A cognitive process involving the repetitive review of information to enhance memory retention.

Related Questions