Table 34 -Using Table 3

question 73

Multiple Choice

Table 3.4
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 2 B 2 C 2 D  A 2 E  B 2 F  B 2 G  C 2 H  E 2 I  F 2 J  D 2 K  I 2 L  K,H 2 M  G 2 N  L, J 2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 2 \\\text { B } & \cdots & 2 \\\text { C } & \cdots & 2 \\\\\text { D } & \text { A } & 2 \\\text { E } & \text { B } & 2 \\\text { F } & \text { B } & 2 \\\\\text { G } & \text { C } & 2 \\\text { H } & \text { E } & 2 \\\text { I } & \text { F } & 2 \\\\\text { J } & \text { D } & 2 \\\text { K } & \text { I } & 2 \\\text { L } & \text { K,H } & 2 \\\\\text { M } & \text { G } & 2 \\\text { N } & \text { L, J } & 2 \\\hline\end{array}
-Using Table 3.4,of the following activities,which one has a slack value greater than zero weeks?