Table 35 -Using Table 3

question 128

Multiple Choice

Table 3.5
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 6 B 3 C  A,B 2 D  A 6 E  C 2 F  D,E 2 G  C 8\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 6 \\\text { B } & \cdots & 3 \\\text { C } & \text { A,B } & 2 \\\\\text { D } & \text { A } & 6 \\\text { E } & \text { C } & 2 \\\text { F } & \text { D,E } & 2 \\\text { G } & \text { C } & 8 \\\hline\end{array}
-Using Table 3.5,how many weeks can activity B be delayed without changing the whole project's earliest completion time?


Definitions:

Team Trust

The belief among team members that their peers’ intentions are good and that there is mutual respect within the team, enhancing collaboration and efficiency.

Collective Efficacy

The shared belief of a group in its joint ability to organize and execute the actions required to achieve specific goals.

Language Skills Training

Education or training programs focused on improving an individual's ability in a particular language, covering areas such as speaking, understanding, reading, and writing.

Role Specialization

The process of assigning specific tasks to individuals or groups based on their skills or expertise.

Related Questions